Sewer Rehab Schedule


The two week schedule for relining of the sewer pipes in Cocoa Beach is as follows:

Monday, March 23, 2015                        Indian Creek Drive

Tuesday, March 24, 2015                       Woodland Avenue
                                                               Oak Avenue at Indian Creek Drive

Wednesday, March 25, 2015                  Naish Avenue

Thursday, March 26, 2015                      Woodland Avenue
                                                               1st Street North at Brevard Avenue North

Monday, March 30, 2015                        Indian Creek Drive
                                                               1st Street North at Woodland Avenue

Tuesday, March 31, 2015                       Cedar Avenue

Wednesday, April 1, 2015                       Bali Road

Thursday, April 2, 2015                           Nassau Road
                                                                Bermuda Road
                                                              