PAVEMENT REJUVENATOR SCHEDULE

The Cocoa Beach Commission approved the funding for rejuvenating the city streets of Cocoa Beach. The work process that will be used will extend the life expectancy of our roads in Cocoa Beach and provide for a smoother ride.The project will take approximately ten days,  but completion is dependent on the weather. Below is Phase I  schedule:

Tuesday, July 21 (Day 1)                                            Day 2
Aucila Drive                                                           Minutemen Causeway
Boca Ciega Road                                                         Day 3
Chipola Road                                                         Azalea Drive
Deleon Road                                                          Bogainvillea Drive
Fairway Drive                                                         Country Club Road
LaRiviere Road                                                      Crystal Drive
Sunset Drive                                                          Danube River Drive
Tom Warriner Blvd.                                                 Woodland Avenue
Willow Green Drive
Day 4                                                                           Day 5
1st Street North                                                        4th Street North
Brevard Avenue North                                              Blakey Drive
Cedar Avenue                                                          Capri Road
Indian Creek Drive                                                    Catalina Blvd
North Shore Drive                                                     Curacau Drive
Oak Avenue                                                              Cyprus Drive
                                                                                  Dempsey Drive
                                                                                  Formosa Drive
                                                                                  MacNabb Pkwy
                                                                                  Naish Avenue
                                                                                  Watts Way

Day 6                                                                            Day 7  
2nd Street North                                                       Antigua Drive
3rd Street North                                                        Esther Drive
4th Street North                                                        Holiday Lane
Bali Road                                                                  June Drive
Bermuda Road                                                          Java Road
Cocoa Isles Blvd.                                                      Samar Road
Nassau Road                                                            Santa Cruz Road
Sunflower Avenue                                                     Trinidad Road

Day 8                                                                          Day 9  
Bahama Blvd.                                                            Andros Avenue
Bimini Road                                                               Escambia Lane
Banana River Blvd                                                     Flagler Lane
Brevard Road                                                             Manatee Lane
Jamaica Blvd.
South Banana River Blvd

Day 10
Ocean Beach Blvd. 

The company, Pavement Technology, Inc,  applying the rejuvenator will be putting door hangers on your door prior to the work beginning.

This is phase one of the project. Phase two will address the rest of the city.