CBNN
Order 12A
No use of private lots for beach access.
Paving map
Project Schedule for Shepard Drive, East Leon Lane and North Banana River Blvd. (see map above).
April 27- Begin milling both East Leon Lane and Shepard Drive. We will begin with East Leon then move to Shepard Drive. Please make sure all cars are off the roadway.
April 28- Paving begins on East Leon and Shepard Drive – beginning on East Leon. Begin milling at the north end of North Banana River Blvd. in southbound lane.
April 29- Begin paving southbound lane of North Banana River Blvd. Begin milling of northbound North Banana River Blvd. Stripping will begin after asphalt is rolled.
April 30- Finish paving southbound lane and start paving northbound lane of North Banana River Blvd. Stripping will begin after asphalt has been rolled.
May 1- Finish paving ,stripping and clean up.
No meal pick ups April 24
CB Community Food Drive
Please give if you can! Online donations accepted at http://www.cocoabeachfire.com/support-us.html
Share on Facebook
Share on Twitter
Share via Email

Copyright © 2017 Cocoa Beach All Rights Reserved.
2 South Orlando Avenue, Cocoa Beach, FL 32931

Powered by
CivicSend - A product of CivicPlus