CBNN

CITY OF COCOA BEACH MAJOR PROJECTS  FY 2022 UPDATE DECEMBER 1, 2021
 

 Water Reclamation

  • Gravity Sewer Rehabilitation Project (16 miles of slip-lining)
Project Cost - $3,332,323 (100% grant from State DEO)
Still awaiting final agreement from DEO.  Project start date is Quarter 1 of calendar
year 2022.
 
Lift Station #17 Generator (Shearwater)Project Cost - $95,000 (75% grant from FEMA-HMGP)
Awaiting final approval from FEMA
  • Reuse Ground Storage Tank Structural Inspections
(Internal/External – scheduled during dry season)
Project Cost - $120,000
  • Lift Station #1 Wetwell Rehabilitation (Plant)
Project Cost - $120,000
Dry Season Project
  • Plant #2 Grit Chamber Resurface
Project Cost - $95,000
Project not scheduled, flexible date
  • Golf Course Outfall Rehabilitation
Project Cost - $250,000
Engineering/Design in progress – Total project timeline is 8/9 months including
construction.
  • Vacuum Truck Purchase
Total Cost - $441,000
Commission approval was November 4, 2021
Build timeline for receipt by June 2022
  • Engineering and Design of Biosolids Project
Total Cost - $255,000
Start Date of February 2022
  • Reclaimed Distribution System Analysis
$180,000
Project in progress

 
STORMWATER
  • North Downtown LID (Burris Way)
Total Cost - $260,000
Project at 90% design
  • McNabb Park Living Shoreline
Completion FY2022
Total Cost remaining ($100,000)
  • Cedar/Woodland/Brevard/2nd Street Improvement
In design
Cost - $75,000
  • Structural Rehabilitation (Outfall pipes/Bioretention)
Cost - $205,000
In progress
  • Ramp Road Design (LID)
Cost - $40,000 (American Rescue Plan Funding)
 
PUBLIC WORKS
  • Minutemen Causeway Shoreline Stabilization Project
Project Cost - $125,000
Engineering proposals requested
  • Mill/Pave N. Brevard (Minutemen to N. 4th Street)
Project Cost - $137,589
Project timeline March 2022
  • Rebuild 2 tennis courts
Project Cost - $200,000
Proposals requested, anticipate completion March 2022
  • Baseball Field Improvements
Joint Project with School Board
City commitment - $150,000
Completion date – February 2022
  • SR 520 Landscaping Improvements-cost $20,000.00


 

Share on Facebook
Share on Twitter
Share via Email

Copyright © 2017 Cocoa Beach All Rights Reserved.
2 South Orlando Avenue, Cocoa Beach, FL 32931

Powered by
CivicSend - A product of CivicPlus