CITY OF COCOA BEACH MAJOR PROJECTS FY 2022 UPDATE DECEMBER 1, 2021
Water Reclamation
- Gravity Sewer Rehabilitation Project (16 miles of slip-lining)
Project Cost - $3,332,323 (100% grant from State DEO)
Still awaiting final agreement from DEO. Project start date is Quarter 1 of calendar
year 2022.
Lift Station #17 Generator (Shearwater)Project Cost - $95,000 (75% grant from FEMA-HMGP)
Awaiting final approval from FEMA
- Reuse Ground Storage Tank Structural Inspections
(Internal/External – scheduled during dry season)
Project Cost - $120,000
- Lift Station #1 Wetwell Rehabilitation (Plant)
Project Cost - $120,000
Dry Season Project
- Plant #2 Grit Chamber Resurface
Project Cost - $95,000
Project not scheduled, flexible date
- Golf Course Outfall Rehabilitation
Project Cost - $250,000
Engineering/Design in progress – Total project timeline is 8/9 months including
construction.
Total Cost - $441,000
Commission approval was November 4, 2021
Build timeline for receipt by June 2022
- Engineering and Design of Biosolids Project
Total Cost - $255,000
Start Date of February 2022
- Reclaimed Distribution System Analysis
$180,000
Project in progress
STORMWATER- North Downtown LID (Burris Way)
Total Cost - $260,000
Project at 90% design
- McNabb Park Living Shoreline
Completion FY2022
Total Cost remaining ($100,000)
- Cedar/Woodland/Brevard/2nd Street Improvement
In design
Cost - $75,000
- Structural Rehabilitation (Outfall pipes/Bioretention)
Cost - $205,000
In progress
Cost - $40,000 (American Rescue Plan Funding)
PUBLIC WORKS- Minutemen Causeway Shoreline Stabilization Project
Project Cost - $125,000
Engineering proposals requested
- Mill/Pave N. Brevard (Minutemen to N. 4th Street)
Project Cost - $137,589
Project timeline March 2022
Project Cost - $200,000
Proposals requested, anticipate completion March 2022
- Baseball Field Improvements
Joint Project with School Board
City commitment - $150,000
Completion date – February 2022
- SR 520 Landscaping Improvements-cost $20,000.00